The first phase linking Phuket Airport and Chalong intersection was discussed at a meeting between Phuket deputy governor Wongsakorn Noonchukhan and MRTA assistant governor Sarot T Suwan on Monday (August 24).
This meeting also heard opinions from local people and businesses as well as the Phuket administration.
The first phase covers 42 kilometres and 21 stations, while the second will cover 16.5 kilometres.
The MRTA will invest Bt35.201 billion for the first phase, with fares set at between Bt35 and Bt140 per trip. Official studies estimate returns of 13.11 per cent for project investors.
The project will be proposed to the Cabinet by mid-2021, with private companies invited to join bidding for contracts in 2022, said the MRTA. Tram services are scheduled to begin operating in 2026.